D.C. Circuit Upholds FERC's Broadview of PURPA | Dorsey & Whitney LLP
On February 14, 2023, the D.C. Circuit Court of Appeals upheld FERC’s broad definition of qualifying facilities (“QF”) under the Public Utility Regulatory Policies Act of 1978...
Stay updated with breaking news from Broadview Solar. Get real-time updates on events, politics, business, and more. Visit us for reliable news and exclusive interviews.
On February 14, 2023, the D.C. Circuit Court of Appeals upheld FERC’s broad definition of qualifying facilities (“QF”) under the Public Utility Regulatory Policies Act of 1978...
Utility industry news and analysis for energy professionals.
Developers saw the ruling as enabling solar projects like Broadview to not only maximize output, but extend solar’s useful hours of availability.
On February 14, 2023, a divided D.C. Circuit panel affirmed FERC’s March 2021 ruling that the power output capacity of a generating facility – not the nameplate capacity of its...
Judges appeared divided on a Midwestern utility's argument that it should not be required to purchase power from a Montana solar facility.