SFGTV September 20, 2013
And the fall of excavation work and 80 Percent Complete on the over all excavation and some of the other highlights that really in zones one and two were completely into the Water Proofing and map slab installation and the director and the pour in zones one and two and in the second half of zone one and two and three. And the thermal and grounding and we have the pictures grounding and the excavation is in full zone. And also into zone four. And the utility work. And it remains, the water system. And we were able to successfully repave it first and the intersections at first and second this pe...