SFGTV December 13, 2013
And good faith effort documentation submitted by all of the three bidders. In our analysis Welsh Construction Company failed to meet the dbe goal or demonstrate the adequate good faith effort. They were advised of that ruling and we had a good faith effort reconsideration meeting on november 27, 2013, they did not provide any Additional Information in writing at the meeting or anything that in essence made us change our decision. So in that regard, Welsh Construction Company was a nonresponsive bid and in researching the work with the legal staff, the California Public code requires that we aw...