By Sue Stafford Tuesday, January 19, 2021 10:59 AM Abbas Drilling put down a well at the east end of Creekside Park. The City has approved funding to complete the project.
photo by Sue Stafford Sisters is adding a new well to its water system, which will substantially increase its pumping capacity.
At last Wednesday’s City Council meeting, the City awarded a public improvement contract to J. P. Prinz Co. LLC in the amount not to exceed $713,317, the lowest of five bids received for the construction of a new Well 4, Phase B.
Phase A, just completed, was the drilling of the well by Abbas Drilling on land at the east end of the Creekside Campground. While Phase A was underway, the design for the well house and all the equipment (Phase B) was being finalized. The well depth ended up being 293 feet. Work included drilling, casing, screening, grout seal, developing and testing as requ