Adelphia Gateway Project Receives Final Notice to Proceed From Federal Energy Regulatory Commission
Phase 2 of project moves to construction
News provided by
Share this article
Share this article
WALL, N.J., May 28, 2021 /PRNewswire/ On May 26, 2021, Adelphia Gateway, LLC received a Notice to Proceed with construction of the second phase of the project from the Federal Energy Regulatory Commission (FERC). The project continues to work closely with local stakeholders and governments as activity gets underway. Adelphia Gateway and its contractors will conduct additional outreach to inform residents and businesses of construction activities in their areas.
Phase 2 construction includes the Tilghman Lateral installation from the interconnect at the Transco Meter Station to its terminus in Chester city, the Parkway Lateral, the Delmarva Meter Station, the Monroe Meter Station and the Tilghman Meter Station – all located in Delaware County, Pennsylvania.