April 08, 2021 Less noisy construction activities at BTO sites may be allowed to be carried out on Sundays and public holidays to speed things up. The Straits Times file SINGAPORE - About 43,000 households will get the keys to their Build-To-Order (BTO) flats late owing to construction delays that are due to manpower shortages and supply chain disruptions. Of the 89 ongoing BTO projects, about 85 per cent are around six to nine months behind schedule, said the Ministry of National Development (MND) in a written parliamentary reply on Monday (April 5). Of the 43,000 affected households as at t...