SFGTV2 February 14, 2013
What we called a concept validation phase where we would contrast the hok scheme with the work being developed by the architect pelly clark pelly to identify any discreptcies in scope and cost and to reconcile those before we moved into the scheme matic design. And so as we moved into the budget and to revise it there were a number of miles stones that we went through. May of 2008, we awarded the contract pelly clark pelly to be the architect and set forth the design schedule at that point which included the concept validation phase that i discussed which was going to be our first four months ...