Manager seeks back pay after Knox County cancels solar contract
The manager claims he is owed $9,549 in lost wages, plus interest. The airport canceled the contract after the firm missed deadlines.
Stay updated with breaking news from Pine Tree Solar. Get real-time updates on events, politics, business, and more. Visit us for reliable news and exclusive interviews.
The manager claims he is owed $9,549 in lost wages, plus interest. The airport canceled the contract after the firm missed deadlines.
OWLS HEAD -- The former manager of the troubled solar farm project at the Knox County Regional Airport has filed a notice of lien against the airport.
Key components of the airport array are being held by the distributor because Pine Tree Solar hasn’t paid its bills for a separate project and customer.
Pine Tree Solar's registration certificate was revoked for not complying with Maine's sales and use tax law, according to a notice.
The revenue services notice is the latest in a list of troubles for Pine Tree Solar.