SFGTV April 19, 2015
Pile lon number 9 this month, so theyre reinforcing and the pylon will start appearing above grade. You can see on the left there, you can see some of the columns sticking up on the bus ramp route from the bay bridge and thats just more reinforcing steel for a column in the lower right and the right side of that. So, pretty much the same progress for the next 90 days, as you heard before, were going the continue the structural steel erection in the central heading east, theyre starting to head west with the second crane in the next 30, 40 days, youll see us crossing 4th street which needs to b...