SFGTV August 18, 2013
The potential or pending change orders, approved change orders, i think was approved somewhere in april 12, so thats what this item is, i would be glad to give you the response to your questions and reasons for these changes, you already have been briefed by julie, the gas tunnel is the water seepage as well as the harder rocks which we are encountering, for your information, the project now is 83 complete. We have lost less of 900 feet to do it, but this seems to be the most challenging at this moment because of the water seepage. Not the harder rock, the water seepage . The harder rock is al...