Bidders day for £4bn-plus Palace of Westminster restoration
Tendering to start next July for main construction, integrator and design partners
Stay updated with breaking news from Renewal Programme Board. Get real-time updates on events, politics, business, and more. Visit us for reliable news and exclusive interviews.
Tendering to start next July for main construction, integrator and design partners
EXCLUSIVE: The mother of all Parliaments is at risk of 'catastrophic and irreversible damage' if it is not fully restored - with patching up the building currently costing the taxpayer some £2million a week. Express.co.uk went inside to have a look.
A report published by the Commons’ Public Accounts Committee on Wednesday (17 May) said there was a ‘real and rising risk that a catastrophic event will
Up to £2m a week is being spent on repairs but there is still a growing list of health and safety incidents.
There is a real and increasing risk that the Houses of Parliament will be destroyed before restoration work has begun, a group of MPs has warned. The