Mayor - News - January 2021 - MAYOR CANTRELL BREAKS GROUND ON $6.7M NEW ORLEANS FIRE DEPARTMENT HEADQUARTERS
And selected removal and maintenance of existing landscaping Phase II will include renovations to the exterior building and interior renovations. Phase I started in December and should wrap up in May 2021, while Phase II will be a nine-month construction project starting in May with scheduled completion by late January 2022. The project team features architect NANO, LLC, contractor Centric Gulf Coast, Inc. (Phase 1), and CPA Project Manager Jennifer Lilos. The Fire Administration, Safety/Community Relations, Fire Prevention, Logistics, Compliance (IT) and Operations Deputy Chiefs will be...