SFGTV February 21, 2015
Additional more than budgeted and that cost was 66,841. The second category is for preconstruction costs with the Transportation Authority and their consultants to coordinate the specifications to new caltrans standards and coordinate the requirements from the city departments that are affected. That cost is 77,787. The next category is just the amount of the contract. The Transportation Authority did a public procurement and received five bids. The award to the lowest responsible bidder was in excess of 180,000 above the amount budgeted. This category alone depleted the project reserves by ov...