SFGTV May 9, 2014
When Webcor Obayashi estimated the plans and a big part of that has to relate to the mechanical and electrical drawings they felt that the amount of conductors and so forth could increase between the 100 percent and the issue for construction documents the hundred percent cds were completed in 2013 so theres a year lag and its a contingency may not be used but its a part of their estimates. If its a percentage thats the highest differential as a percentage and you would think that design contingency since basically our designers are in place and everything that would be the lowest if anything ...