SFGTV January 6, 2011
the work involved is necessary prior to the excavation because it creates the waterproofing of the area. shoring work needs to be completed before we can move into excavation. we have looked at the critical path submitted by webcor. that represents a day for day delay on the delivery of the project. if we were to wait one month to vote on the item, we would be delayed the entire project by one month. also, in the event that there might be a delay, looked at the baseline schedule to see if we could we sequence work to take this off of the critical path. we have got through exercises a...