Ten month schedule to ready SLS for Artemis 1 launch after Core Stage arrives at KSC


Ten month schedule to ready SLS for Artemis 1 launch after Core Stage arrives at KSC
May 3, 2021
NASA’s Exploration Ground Systems (EGS) program is looking at a wide range of forecasts for when they can complete testing necessary to be ready to launch Artemis 1. The Core Stage of NASA’s first Space Launch System (SLS) vehicle arrived at the Kennedy Space Center and was moved into the Vehicle Assembly Building (VAB) on April 29 to prep for stacking with the new launch vehicle’s Solid Rocket Boosters, which are already in place on the Mobile Launcher in High Bay 3.
Approximately six months of work is anticipated to finish assembly and complete a long series of tests and checkouts of SLS and the Orion spacecraft it will send to the Moon, but current forecasts of this first-time integration work estimate closer to ten months to complete the necessary operations. After the vehicle is put together, weeks and weeks of testing to make sure SLS and Orion are properly talk ....

Launch Complex , United States , Cliff Lanham , Andrew Shroble , Michael Alldredge , Nathalie Quintero , Philip Sloss , Exploration Systems Development , Tail Service Mast Umbilicals , Stennis Space Center , Operations Aerospace , Kennedy Space Center , Vehicle Assembly Building , United Launch Alliance , Ground Systems , Core Stage , Space Launch System , Solid Rocket Boosters , Mobile Launcher , High Bay , Vehicle Operations , Shuttle Main Engines , Integrated Testing , Wet Dress , Multi Payload Processing Facility , Core Stage Green Run Hot Fire ,