SFGTV Government Access Programming July 14, 2024
Convert that wet weather facility into an allweather facility, which would require us to do extensive sewer diversion work and impact the traffic on the road there. As soon as we onboarded a cm gc contractor, we started to get feedback from them and first major input was to remove that underground line which is 78inch and was on the piers to an aboveground 54inch hdp line on the road. That helped us to reduce significant risk associated with the congestion in the plant road and eliminating conflict with the seismic work. The second major collaboration between cm gc and designers was to move th...