N.Y. PSC Issues Order on Waiver Requests Involving Alle-Catt Wind Energy


Targeted News Service
ALBANY, New York, May 19 (TNSsre) The New York State Public Service Commission issued the following order on waiver requests (Case No. 21-T-0059):
In the Matter of Alle-Catt Wind Energy LLC for a Certificate of Environmental Compatibility and Public Need Pursuant to Article VII of the Public Service Law.
ORDER ON WAIVER REQUESTS
INTRODUCTION
On February 10, 2021, Alle-Catt Wind Energy LLC (ACWE) filed an application (Application) for a Certificate of Environmental Compatibility and Public Need (Certificate) pursuant to Article VII of the Public Service Law (PSL). If granted, the Certificate would authorize ACWE to construct, operate, and maintain a new overhead 345 kV electric transmission line and associated equipment (Transmission Facility) located in the towns of Freedom and Yorkshire in Cattaraugus County. The Transmission Facility would interconnect the Alle-Catt Wind Farm/1 to a new 345 kV switchyard built adjacent to National Grid ....

New York , United States , Town Of Yorkshire , York State Public Service Commission , Public Service Law , Department Of Transportation , Public Service Law Article , National Grid , National Geospatial Program , Us Geological Survey , York State Department Of Transportation , United States Geological , Catt Wind Energy , New York State Public Service Commission , Alle Catt Wind Energy , Environmental Compatibility , Public Need Pursuant , Public Service , Public Need , Transmission Facility , Alle Catt Wind , Stolle Road , Five Mile Road Substations , United States Geological Survey , New State Department , Proposed Rulemaking ,

Farmersville facing Alle-Catt lawsuit over voiding road-use agreement


FARMERSVILLE — Alle-Catt Wind Energy LLC has filed a lawsuit in Cattaraugus County Supreme Court against the Farmersville Town Board over the voiding of a road-use agreement required to build the proposed 340-megawatt Alle-Catt Wind Farm.
In an Article 78 lawsuit, Alle-Catt asks the court to rule that the town board’s Oct. 12 action voiding of the 2019 road-use agreement was an “unlawful termination” of a “binding and valid agreement.”
Town Attorney Eric Firkel said, when the board voted in favor of the road-use agreement in 2019, “They ignored Local Law 2 of 2001, which said no vehicle weighing more than 8 tons” could be driven on town roads except for pickup and delivery. Public utilities were excluded. ....

Eric Firkel , Terrence Parker , Mark Heberling , Supreme Court , Cattaraugus County Public Works Department , Cattaraugus County Supreme Court , Catt Wind Energy , Alle Catt Wind Energy , Farmersville Town Board , Alle Catt Wind , Attorney Eric Firkel , Local Law , Deputy Supervisor Mark Heberling , Ginger Schroder , Farmersville United , Town Board , Judge Terrence Parker , Term Limits Doctrine , Schwab Dairy Farm , டெரன்ஸ் பார்க்கர் , உச்ச நீதிமன்றம் , கட்டார்துக்ஸ் கவுண்டி பொது வேலை செய்கிறது துறை , கட்டார்துக்ஸ் கவுண்டி உச்ச நீதிமன்றம் , கேட்ட காற்று ஆற்றல் , அல்லே கேட்ட காற்று ஆற்றல் , விவசாயிகள்வில்லி நகரம் பலகை ,