SFGTV March 13, 2015
Yes. All right, Public Comment on this item. I will call for the vote. All those in favor . Opposed . The motion carries. Next item. Item 13 approve an increase in the construction contract cost contingency for contract no. Wd2641r in the amount of 522,328 and increase in the contract duration of up to 376 consecutive calendar days and authorize future modification to the contract. Emilio cruz, assistant general manager contractor. In this case we know we have an a15 tif delay. This is primarily because of the Drought Conditions and the need to bring in additional water. As part of the wisa pr...