Work activities. Just moving right along very well. Shimmick is doing a great job with the schedule on that. Current work in the western zone, the focus on the upper left was getting the lower concourse cleaned out after the train box level all cleaned after placing the lower concourse work. On the righthand side you may wonder what were using styrofoam for . That is the beginning of the form work and that is much further along here in june. That is also within the shimmick 6. 0 contract to complete the ramp up to the surface and the first portion of it, the form work is done with the styrofoa...