KUSA 9News 6pm Next September 1, 2016
5 weeks leading up to opening, they put trains on the line to test the system and kept to the schedules they have now, but with no passengers, the goal, explained in the contract with denver transit partners, was to get a testing score of 95 or above on 21 consecutive days. You didnt come anywhere nee that. No. Reporter spokesperson, instead of geting to the goal of 21 days of 95 or above like this, the aline delivered but 6 passing days in all. 6. That is it. And still, the aline opened up on time, on april 22. Reed said he knows what you are thinking, but. We knew that going in, it would be ...