SFGTV Transbay Joint Powers Authority 10815 October 18, 2015
October. Central zone we have a lot of concrete pored so the other trade contractors, mechanical, electrical and plumbing and stair and other contractors are starting to mobilize into the area so this area is having interior walls built out and electrical and plumbing trade recess still continuing on installing some of the hangers above head. And the roof level slabs are the main focus. We have slabs pored on the roof but continuing with grid lines ten and 20 and pored to grid line 50 and focused this month of october is to continue that concrete pores towards the east ends of that central zon...