SFGTV Government Access Programming January 13, 2018
From all of the Funding Partners. So, moving on to the schedule. You will see here its a bit small. The gray represents milestones that have been achieved. The blue represents to be achieved milestones. Where were at now is were in this intensive construction phase. We look to receive our first train set on property in late 2019. And then from the time that we receive that first train through the commencement of Passenger Service we will be completing the electrified system. We will be completing it and bring us to Passenger Service in early 2022. So, if you have certainly any questions in bet...