Approving an amendment to contract no. 0804cmgc000, authorizing Webcor Obayashi joint venture to award a trade work subcontract to clayton coatings, inc. As the responsible bidder submitting the lowest responsive bid in the amount of 8,594,839 for tg16. 8 fireproofing, thereby increasing authorized direct costs by 8,594,839, and the authorized Construction Services fixed fee by 653,208. Mark savana will report on this item. Good morning directors and i have a short presentation that i present to you and i can answer any questions, which do you prefer . Actually just a very short couple of sent...