SFGTV Government Access Programming November 28, 2017
The order of 20 million on a preliminary basis. More flexibility with Priest Reservoir supply and also hydro power benefits which are currently under evaluation. And so the schedule for this project would be essentially to begin our ceqa and nea process immediately. That would take a little over two years. In parallel, we would do our design process and also the rightofway accusations that are needed for the project for staging areas and access and we would expect to issue notice to proceed on construction in the spring of 2020. At that point, the contractor would mobilize and start doing the ...