SFGTV November 18, 2013
Weve skaeftd excavated over in our last meeting we briefed some unanticipated geology conditions that were encountered on the left side of the valley on the spill way. Since our last update we have issued a 7. 4 million lateral order to keep the contractor working on that side of the valley and to prevent us from accumulating any major delays on the project. We anticipate getting a proposal from the contractor for addressing these new conditions by the end of the year. Well then probably need a couple months to negotiate that change order. So our goal is to have a finalized change order by mar...