SFGTV July 10, 2013
Million to 7. 755. For work that has already been completed. Shall i go to the next two items . Yes. Regarding item 4, on page 22 of our report, we report that its shown in table on page 22, the contractor delta star has submitted invoices and all of the repairs were complete on february 12, 2013. Such that no expenditures will be incurred. Our recommendation on the bottom of page 22, that you recommend the proposed resolution on february 12, 2013, instead of january 2013. The work includes all three phases and that you approve the proposed resolution as amended. Regarding item 5, on page 29 o...