SFGTV August 7, 2014
Implemented a strategy for the caltrans plus a plus b where the bidders bid to schedule as well as the cost of the project. As it turned out the low bidder presented a schedule that was a year less than what we previously scheduled so that improved the schedule for the bus ramps by a one year period. We have implemented a number of lodging changes and shorter schedule durations within the current schedule to keep the project on track. And we have resequenced the design submittal packages for earlier bidding of selective trades. So there are a number of mitigation strategies we have available t...