SFGTV July 10, 2013
A i can give a little bit of background for this project in particular. When we started the environmental phase of the geary project, the estimate to complete the phase of work was for about 6 Million Dollars. But we didnt request all that those funds at once. We requested installments as we did the work and as it became khroerer what remaining work needed to be done. So weve cock come back to the plans committee and the full board periodically throughout this phase as weve made more progress and clarified what, again, more work needs to be done. The total phase of this work where were estimat...