SFGTV January 9, 2014
Amendment request for today. And which we would complete the precom services through 2015. Back in 2009, is when the cmgc agreement was reached with web cor, and that at the time there was no train box, the train box was added in 2010 and eventually that services were included by 2011, Preconstruction Services were amended by amendment 20 to include the scope of that work. Since that time, there was items such as the risk and vonnerbility assessment that was added and had to reevaluate and remodel and modify a lot of the design in the project. And which also affected the design delivery, as we...