Yes, jessica and natasha, the Construction Company responsible for building the new dorm got back do me say that this delay was all caused by a design that required additional testing to meet California Building code. They have been running double shifts for the past couple of months to expedite the process. They are simply not ready for this weekend move in day. Moving is never easy but san jose state did not think it would look like this, rather than welcome 820 freshmen into the brand new ten story high recognize students were notified yesterday they will have to live here in the bricks. I ...