SFGTV February 14, 2013
Here and when we discovered these features back in mid 2012, production on the project was impacted by four months essentially. But since then we have picked up and we are moving ahead full speed right now on the project. We are 35 done with the project. And id like to highlight the fact that the sods 117 million we are asking to you approve today to transfer to the project will only cover the construction, the increase in Construction Costs. There will be a need for increases also what we call the soft costs, delivery costs for the additional 25 months. And there are also significant risks re...