SFGTV December 28, 2012
At the end of the west end of the project. The awss work continues on Mission Street. They were able to get an exemption from the holiday moratorium to allow them to continue that work. So well finish that early part of next if year as they work through the holidays on mission continuing to put in the new water line. Coming up next, the belowgrade structure contractor who now has the geothermal and grounding contracts within their package will start that work in january. The buttress work will continue and the micro pile production, they completed 70 in the total production piles and that will...