Obtained. The federal Highway Administration gives caltrans the green light to open the bridge by labor day as originally planned. We see no reason to delay opening the bridge to traffic. Those words clear the way for caltrans to install a temporary fix for the 32 busted bolts on the bridge. Caltrans would strategically place them to keep them from moving up and down. The shims are adequately replace the function of the failed anchor rods. The time line, up to a week and a half to install the shims and another 2 to 4 weeks to notify the public, airports, and businesses about the change. That m...