SFGTV January 15, 2013
Incidents on the project. We have you saw the 700,000 plus man hours todate throughout the entire project and taking into account the current work on the Transit Center, all the work under webcors contract, 600,000 craft hours through the end of 2012. And that is about 38,000 completed over the last period. The most significant progress has been made in the excavation and there is some statisticks there of where we are. The ultimate news is that were about 50 complete with the overall excavation of the project. You heard 27 5,000 cubic yards have been removed. So were right on track. There som...