CSPAN Capital News Today July 1, 2011
i do not know if that is accurate or not. that is the way i read the numbers. in your testimony, you attributing this to the security environment. you responded to this shares questions about the security environment. what is the cost overrun excluding security costs. >> let me clarify it in little bit. that was our estimate we thought at the time it would cost to build that road. the bids that came in and the firm that won the contract came in at $85 million to $86 million. that was the starting point for us of the construction, not counting security for the construction management....